The production units in the company are focusing all resources on synchronously implementing solutions to improve productivity, ensure progress and quality of handover to the investor. Although the first months of 2022 due to the impact of the Covid-19 epidemic, the Company still maintained continuous production, the result was that most of the projects were completed and handed over to the investor. on schedule.
1. Fabrication and installation of Line No.3 Xuan Thanh Cement Plant with a capacity of 12,500 tons of clinker/day: In 2018, after completing production Line No.2 with the high quality and on time progress, Lilama 69-3 is trusted by the investor, Xuan Thanh Cement Joint Stock Company, to continue awarding a contract to manufacture and install Line No.3 with the same capacity and volume as Line No.2, but the execution time is shorter than before. The expectation of operation process Line No.3 is expected to be in August 2022.
Installing Line No.3 Xuan Thanh Cement Plant, Ha Nam province capacity 12,500 tons of clinker/day
Installation of Kiln shells
The area of Kiln installation
2. Manufacturing warehouse equipment exported to Japan for a thermal power plant - Takraf project:
- Fabrication of 04 Potal Reclaimer machines of 1,291 tons for Takraf GmbH (Germany) exported to Japan - IUK Chubu Taketoyo Thermal Power Plant project - ensures the progress (from July 2018 to May 2020)
- In August 2020, continue to manufacture 04 Stacker machines & 04 Portal Reclaimer machines of 2,600 tons for Takraf India Private Limited (India) to export to Bangladesh - The key coal-fired power project Matarbari – Bangladesh. Up to now the company has completed production and delivery of the last shipment on 30 April, 2022.