ACCELERATION OF THE PROGRESS OF LOCAL PROJECTS AND EXPORT PROJECTS IN 2022.

Wednesday - 18/05/2022 05:47
To ensure the completion of projects in accordance with the 2022 plan and the progress of the projects.
The production units in the company are focusing all resources on synchronously implementing solutions to improve productivity, ensure progress and quality of handover to the investor. Although the first months of 2022 due to the impact of the Covid-19 epidemic, the Company still maintained continuous production, the result was that most of the projects were completed and handed over to the investor. on schedule. 
1. Fabrication and installation of Line No.3 Xuan Thanh Cement Plant with a capacity of 12,500 tons of clinker/day: In 2018, after completing production Line No.2 with the high quality and on time progress, Lilama 69-3 is trusted by the investor, Xuan Thanh Cement Joint Stock Company, to continue awarding a contract to manufacture and install Line No.3 with the same capacity and volume as Line No.2, but the execution time is shorter than before. The expectation of operation process Line No.3 is expected to be in  August 2022.
100
Installing Line No.3 Xuan Thanh Cement Plant, Ha Nam province capacity 12,500 tons of clinker/day
11
Installation of Kiln shells
13 3
The area of Kiln installation
2. Manufacturing warehouse equipment exported to Japan for a thermal power plant - Takraf project:
- Fabrication of 04 Potal Reclaimer machines of 1,291 tons for Takraf GmbH (Germany) exported to Japan - IUK Chubu Taketoyo Thermal Power Plant project -  ensures the progress (from July 2018 to May 2020)
- In August 2020, continue to manufacture 04 Stacker machines & 04 Portal Reclaimer machines of 2,600 tons for Takraf India Private Limited (India) to export to Bangladesh - The key coal-fired power project Matarbari – Bangladesh. Up to now the company has completed production and delivery of the last shipment on 30 April, 2022.
14 333
 
15
Pictures of equipments manufactured by  Lilama 69-3, installed at Thermal power plant - Bangladesh, under the Takraf India project.

3. Fabrication, installation and repair of equipment for heavy industrial plants.

16 333


17 33
18 33








     



























 

Total notes of this article: 0 in 0 rating

Click on stars to rate this article

  Reader Comments

Catid
Developing export markets and diversify mechanical products.
This is one of the important contents directed by the Company's General Director in the briefing meeting at the end of 2023. Identifying mechanical...
Lilama 69-3 has completed many projects to ensure "PROGRESS - SAFETY - QUALITY" through 2022.
With the goal of speeding up the implementation of projects, focusing on exploiting strengths in processing, manufacturing, installing mechanical...
Three major domestic projects, important highlights in 2022.
1. Ahead of schedule, ensuring Safety - Quality for "Heart of the factory": This is the item of Clinker Kiln Line No.3, Xuan Thanh Cement Plant with a...
ACCELERATION OF THE PROGRESS OF LOCAL  PROJECTS AND  EXPORT PROJECTS IN 2022.
To ensure the completion of projects in accordance with the 2022 plan and the progress of the projects.
You did not use the site, Click here to remain logged. Timeout: 60 second